Contract DM 03, Contract DM 04 & Contract SZR-2
Client : Tabreed, National Central Cooling Co. (PJSC).
Consultant : Cassia & Partners (For SZR-2) / Eng. Adnan Safarini (For DM03 and DM04)
Main contractor : SNC – LAVALIN GULF CONTRACTORS L.L.C.
Value : AED 95.8 Million
Duration : October 2006 – September 2009
Location : Dubai
THE CHALLENGE
The largest mall in Al Ain, this project is basically a multipurpose development that comprises a 145,000 m2 shopping mall housing 400 retail outlets. The latter were handed over in ‘shell and core’ state to enable the fit out works of leading brands such as:
• Contract DM03 – Al Rashidiya
• Contract DM04 – Al Kifaf
• Contract SZR-2- Sheikh Zayed road
The SZR2 project is located nearby the prestigious Burj Khalifa and is designed to supply chilled water for Business Bay metro station and other surrounding towers.
It is designed for a capacity of 35000 T using 20 chillers and equipped for future expansion.
NCC has carried out these projects on a turnkey basis, including the foundations, structure, architectural and finishing works.
SCOPE OF WORKS
• Foundations, sub structure and super structures
• Architectural works
• Chambers and lifting stations
• Entire HVAC system
• Fire detection and protection system
• All Mechanical, electrical and plumbing
• Testing and commissioning